Club House Restoration Status – April 14, 2018

April 14, 2018: Garry Woodhouse has advised the clubhouse is nearly finished. Furniture when in today! April 9, 2018: Jim Keil has advised Post – Harvey restoration work is progressing on the Bayou City Flyers Club House. As of April 9, 2018, additional wood framing has been installed around the door and windows, T-111 wood paneling has been installed on the interior walls, primed and painted. Window trim has been installed, two drip pans have been installed below the leaking roof vents and plumbed to drain outside with ceiling insulation and ceiling tiles installed. Installation of carpet squares has begun and when completed the carpeting will be shampooed and the baseboard trim installed. Thank you to the small but very dedicated group of club members that have completed this work.